ACTIVITY_GRAPH_TIME_EXAMPLE
The scenario presented is a list of tasks/activities that need to be performed in the ‘project’ of obtaining employment. Generate an activity graph and determine the critical path and the least amount of days necessary to obtain a job. (Note please review all tasks as they may not be listed in sequential order and it is best to label them starting with task A)
Identify specific career field(s) 3d
Create Resume 1d
Edit Resume .5d
Print Resume(s) 2d
Contact References 2.5d
Set appointment with recruiter 3d
Engage in recruiter appointment .5d
Research newspaper ad .5d
Research internet 1d
Develop contact list .5d
Call Existing contacts 3d
Create list of new contacts/opportunities 1.67d
Call New Contacts 4.67d
Set up interview 2d
Conduct interview (s) 3d
Send thank you note .5d
Consider job offers 2d
Accept job .5d